28 October 2023

Consultation day onsite at Tunes In The Trees

We will be at Tunes in The Trees at Woombah Park from 2 pm to 4 pm hear all of your great ideas and suggestions!!!

01 November 2023

Chatsworth Island Public School Consultation

We will seek feedback from our most important design consultants the Chatsworth Island Public School kids on Wednesday 01 November at 2 pm.

26 October → 30 November 2023

Community Consultation - Evaluation and Review

Community consultation is closing on 30 November 2023. This feedback will be the key design drivers for the project.

01 December 2023 → 30 March 2024

Playground design approval

The detailed design of this project will be completed and approved by the end of February 2024. From there we can go out to quote to engage contractors and internal staff to begin the project. 

01 April → 28 June 2024

Site works

Estimated project delivery timeline 

30 June 2024

Project completion

Council is confident that the project will be completed by the end of the 2024 financial year.